Weekly Column: Working for a Safer, More Efficient Transportation System

The following is my column that will appear in this week's Mt. Vernon Gazette in the week of August 1, 2022.   

Working for a Safer, More Efficient Transportation System

This is an update on several important transportation projects underway in our area, including the U.S. 1 Speed Study, undergrounding utilities on U.S. 1, the I-495 Southside Express Lanes Study, and the Youngkin Administration’s reallocation of transit funds.

Since 2017, we have seen the following on U.S. 1 in Fairfax County:

  • 1,785 crashes
  • 1,185 injuries
  • 15 deaths

The per-lane-miles-travelled accident rate between Fort Belvoir and Hybla Valley is 70% higher than the Virginia and Fairfax County averages.  From Hybla Valley to Alexandria it is 40% higher. These are troubling numbers.  The $800 million widening of U.S. 1 and construction of bus rapid transit will bring significant safety improvements and is being engineered with lane widths assuming a 35 MPH speed limit.

Friday, May 28, 2021

Investing in Southeast Fairfax Infrastructure

 Today, Delegates Kathy Tran and Paul Krizek joined me to submit a request to our federal
representatives for infrastructure investments in the U.S. 1 corridor. Please read our letter below.

We requested funding for undergrounding utilities on U.S. 1 and replacing the obsolete bridge on Old Colchester Road over Giles Run.

Our region has long suffered from underinvestment in crucial infrastructure that would spur private sector development and provide necessary access to services for our community. In the coming years, over $1 billion will be invested in the 36th District. The tide is beginning to turn but we have a long way to go. 

I am hopeful that the federal government will play a role by investing in these requests. Investments made today will pay dividends for the next generation of U.S. 1 residents and small business owners.

Earmark Request for U.S. 1 ... by Scott A. Surovell

Sunday, January 31, 2021

Weekly Column: Virginia Legislature Is Moving Bills, Addressing Problems

The following is my column that will appear in the Mt. Vernon Gazette, Springfield Connection, The Prince William Times, The Fort Hunt Herald, and Potomac Local in the week of January 31, 2021.

Virginia Legislature Is Moving Bills, Addressing Problems

As the General Assembly begins its fourth week in session this year, vaccine deployment for Covid-19 has started to accelerate and we are discussing how to jump-start in-person schooling.  Virginia’s Secretary of Education believes all school personnel will be vaccinated by March 1 and a bill is pending to require in-person elementary-secondary school options no later than July 1.  Depending on how discussions go, the General Assembly might pass a mandate to require in-person learning sooner.

Tuesday, May 19, 2020

Fairfax County BRT/U.S. 1 Widening Update

Today, Fairfax County's Department of Transportation provided an update on the status of the U.S. 1 Bus Rapid Transit Project and U.S. 1 Widening.

Richmond Highway Widening Update



  • They have been developing responses to public comments
  • Incorporated minor design adjustments
  • Meeting with property owners
  • Working on right of way plans
  • Conducting title research
  • Design changes

    • Two way cycle tracks
    • Bridge features modified
    • Change from bridge to a pre-cast arch
    • Section adjustments to accomodate larger trees
    • Plaza designs at intersections
    • Raised driveways along U.S. 1
    • Reviewing viability of stormwater management facility enhancements

  • Schedule Revisions

    • Project has been delayed one year
    • Design approval in 2019 did not happen
    • FONSI planned in Fall, 2019 - didn't happen
    • ROW acquisition was supposed to start in Winter, 2019 and did not
    • ROW/Utility Relocation seems to be taking longer-6 years instead of 3.5 years

  • Design approval was expected but did not

    • Fairfax County has not approved design
    • Ongoing design features need to be resolved (stuff above) along with construction of BRT project with this
    • Approval was submitted in 11/19 but delayed due to a Title VI complaint that was initiated
    • VDOT did receive conditional design approval except for the Little Hunting Creek Underpass